PMAY-G MIS Report 2026: Houses, Allocation & Total Budget
The PMAY-G MIS report is the Ministry of Rural Development’s running count of PM Awas Yojana-Gramin. MIS stands for Management Information System. It shows how many houses each state was given, how many it approved, and how many were finished. It does not show your name, and it is not a beneficiary list.
Three words carry almost every number in it. Read them right and the rest of the report makes sense.
Target, Sanctioned, Completed: The Words That Run the Report
| Word in the report | What it means | Who controls it |
|---|---|---|
| Target (allocated) | Houses the Ministry has given a state to build | Ministry of Rural Development |
| Sanctioned | Houses the state has approved for named families | State government |
| Completed | Houses finished and verified on the ground | Built by the family, confirmed by officials |
The gap between each pair tells its own story:
- Target minus sanctioned: houses a state has been given but not yet approved for anyone. A large gap usually means families are still being verified.
- Sanctioned minus completed: houses approved but still being built. These families are waiting on installments or on construction.
A common confusion: “allocation” in news reports almost always means the target, not money and not completed houses.
Where the Count Stands Nationally
PMAY-G began on 1 April 2016 with a target of 2.95 crore houses by March 2024. In August 2024 the Union Cabinet added 2 crore more houses for April 2024 to March 2029. That makes the overall goal 4.95 crore houses.
Not all of that has been handed to states yet. A Ministry reply in the Lok Sabha gave the position as of 3 August 2026:
| Measure | Houses |
|---|---|
| Overall goal to 2029 | 4.95 crore |
| Target allocated to states so far | 4.18 crore |
| Sanctioned by states | 3.91 crore |
| Completed | 3.12 crore |
| Sanctioned, still under construction | about 79 lakh |
In FY 2025-26 alone, 32.47 lakh houses were sanctioned and 26.57 lakh completed. Those yearly figures include houses whose targets came from earlier years.
These totals move every month. The Ministry also notes that at least 60% of the PMAY-G target is earmarked for Scheduled Caste and Scheduled Tribe households, where eligible families are available.
Allocation: How Houses Reach a State
The Ministry does not hand out all 2 crore new houses at once. It releases targets in tranches, state by state.
For FY 2024-25, the target was 84,37,139 houses. Of these, 46,56,765 were allocated in December 2024 and January 2025 to nine states, including Assam, Bihar, Chhattisgarh, Jharkhand, Madhya Pradesh, Maharashtra and Rajasthan, according to a Lok Sabha reply.
A state’s target then depends on its eligible households. Those come from the SECC-2011 list, the Awaas+ 2018 list, and now the Awaas+ 2024 survey. A state that has covered its older lists gets new targets only as survey families are verified.
This is why two states can look very different in the same report. Uttar Pradesh has sanctioned nearly its whole old target, as the UP Awas Yojana list page shows. Jharkhand is one of four states still covering families from its older lists.
The Money Behind the Houses
Searches for the “total budget” usually mean one of three numbers. They measure different things.
- Five-year outlay (2024-25 to 2028-29): ₹3,06,137 crore, approved by the Union Cabinet. That splits into a Central Share of ₹2,05,856 crore and a State Matching Share of ₹1,00,281 crore.
- Central share released since 2016: ₹2,49,569.76 crore, as stated by the Ministry in March 2025.
- Releases this year: for FY 2026-27, the Ministry issued a “mother sanction” of ₹11,121 crore, then another ₹10,021.42 crore to 12 states on 28 May 2026.
How the cost of each house is shared:
| States | Centre : State |
|---|---|
| Plain-area states | 60 : 40 |
| North-eastern states, Himachal Pradesh, Uttarakhand, UT of Jammu & Kashmir | 90 : 10 |
| UTs without a legislature | 100% Centre |
Each family gets ₹1.20 lakh in plain areas and ₹1.30 lakh in hilly states, north-eastern states and difficult or IAP districts. The Cabinet approval keeps 2% of programme funds for administration.
Opening the MIS Report Yourself
The reports sit on the PMAY-G reports site, report.pmayg.dord.gov.in. They are grouped into lettered sections, each a set of tables. One example is “H. Social Audit Reports”.
What you can use it for:
- Comparing states: targets, sanctions and completions side by side.
- Seeing progress over time: whether a state’s sanctioned-but-unbuilt pile is shrinking.
- Checking news claims: a headline number should match the report for the same date.
What you cannot do there:
- Find your own name: individual records are searched by registration number on the beneficiary search page, not in MIS tables.
- Download a state list PDF: no official state-wise beneficiary PDF is published. The old “Beneficiary details for verification” report is no longer on the site.
- Track your installment: payment checks for one family use the FTO page, explained on the PMAY-G installment check page.
What the Numbers Can’t Tell You
MIS tables are counts, and counts hide some things worth knowing before you draw conclusions:
- “Completed” is a status, not a quality check. It means the house was recorded as finished in the system, not that every family is satisfied with it.
- Yearly figures overlap. A house sanctioned in 2024 and finished in 2026 shows up in two different years’ columns.
- Dates matter. A figure without its “as on” date can’t be compared with another one. Always compare totals from the same day.
- Urban houses are elsewhere. PMAY-Urban 2.0 numbers live on pmaymis.gov.in, a different system. Adding the two from separate reports mixes different dates and methods.